Project information

  • Period : 2025-Now (On Progress)
  • Project :
    Major Overhaul (MOH) Cirebon #2 CFCC
  • Client :
    Toshiba Plant Systems & Services Corporation (TPSC ENGINEERING INDONESIA)
  • Location :
    Cirebon #2 Coal Fired Power Plant

Project Description

Cirebon #2 Outage Work & Major Overhaul

  • CW Pipe Water Leak Repair Work
  • Condenser Water BOX #A Inlet Flange
  • Service Water Pipeline Header (Turbine Ground Floor Area)
  • HP Heater #6 Extraction NRV After Drain Valve Weld Connection
  • LP Heater #4 To Deaerator Drain Line Valve
  • LP Heater #4 To Deaerator Vent Line Valve
  • Repair Before/After Seat Drain Valve of MSV#A, B, C, and D